Converting Documents to BIM Record Drawings Using Integrated Project Delivery

SCROLL

Project Delivery Method: Integrated project delivery (IPD)


Project Type: Infrastructure improvements


Owner Team: Company CEO, building committee (preselected building managers), corporate leasing manager, corporate capital projects manager, and corporate facility manager


Project Delivery Team: IPD building information modeling (BIM) services consultant


Individual On-Site Project Teams: Building manager and facility manager

2019 HVAC Applications ASHRAE Handbook: Chapter 41, Computer Applications; Chapter 66, Codes and Standards; and Chapter 60, IPD and Building Design


Other References: U.S. General Services Administration (GSA) guidelines for BIM software and International Organization for Standardization (ISO) BIM standards

DESIGN INTENT DOCUMENT (DID)

  • An international commercial building institution makes a corporate decision to update all of its building record drawings to 3D BIM computer-aided drawings (CAD)
  • This institution makes a corporate decision mandating all future building programs shall be completed using 3D BIM CAD software to generate contract drawings
  • BIM standards shall include the institution’s standard layers documenting operation and maintenance data, e.g., architectural flow plans with all water systems shut-off valves located on the drawing.

Program Goals

  • Functional Goals: operation and maintenance documentation and safety and security documentation
  • Future Construction Documentation BIM Application Goal:
    • Design concept phase — architect-engineer (AE) consultants per project
    • Design development (DD) phase — AE
    • Construction documents (CD) phase — AE
    • Construction delivery phase – general contractor (GC), construction manager (CM), or IPD team, per project
    • Closeout phase (as-built and record drawings) — GC / AE
  • Timeline Goal: To be completed at each of the institution's 20 commercial sites by June 2022
  • Maintenance Goal: To be in sync with the institution’s computerized maintenance management software (CMMS) system
Motor vehicle, Product, Font, Line

DESIGN CRITERIA DOCUMENT

  • The IPD team, including each building’s office manager, building facility manager, and third-party BIM service consultant, will facilitate the project
  • The IPD approach will include architectural, structural, HVAC, plumbing, fire protection, electrical, and telecommunication record drawings
  • The IPD team, which includes corporate management’s building committee of building managers, the leasing manager, capital projects manager, and facility manager — along with a new corporate BIM manager — will design-construct, operate, and maintain BIM contract document standards for all future capital projects, new and tenant fit-out
  • The IPD team BIM standards shall include a separate leasing agreement layer documenting the square footages, lease start and end date, and cost per square foot
  • The IPD team will establish BIM security and a resiliency layer that will include the site plan showing potential security concerns, e.g., air intakes
  • Each building’s facility manager/staff will assist in confirming the location of equipment and devices, e.g., smoke dampers, fire alarm devices, etc., in sync with the other team members documenting existing conditions.  
  • Two-dimensional building elevations shall not be used
  • The BIM service consultant shall coordinate a barcoding process in sync with the corporate facility manager’s CMMS system population of equipment with bar codes
Fixture

Image courtesy of WSP USA

Hard hat, Workwear, Plant, Engineer, Headgear

Image courtesy of Pixabay.

Design Engineer’s Punchlist

Project Delivery Method:

  • Design-Build (D-B)
  • Integrated Project Delivery (IPD)
  • Construction
  • Design-Bid-Build (D-B-B)
  • Performance Contract (PC)

Owner Team:

  • Company CEO
  • Building Committee
  • Owner Representative
  • In-House Architect

Project Delivery Team:

  • Construction Manager
  • BIM Services Consultant
  • BIM CAD Operator
  • O&M Staff
  • Individual On-Site Project Team Members
  • Government Agency

Application 2019 ASHRAE Handbook

  • Fundamentals 2017 Handbook
  • Refrigeration 2018 Handbook
  • HVAC Applications 2019 ASHRAE Handbook
  • HVAC System and Equipment 2020 ASHRAE Handbook

Other References:

  • Codes and Standards in the Back of Each ASHRAE Handbook for Additional Information
  • U.S. General Services Administration (GSA) Guidelines for BIM Software
  • Construction Management Association of America (CMAA)
  • International Organization for Standardization (ISO) Building Information Modeling Standards

DESIGN INTENT DOCUMENT

  • A Commercial Building Institution Makes a Corporate Decision to Update all its Building Record Drawings to 3D BIM Computer-Aided Drawings (CAD)
  • This Institution Makes a Corporate Decision to Mandate All Future Building Programs Shall Be Completed using 3D BIM CAD Software to Generate Contract Drawings
  • The Project Delivery will Be Design-Bid-Build for All Future Projects
  • BIM Standards Shall Include the Institution’s Standard Layers Documenting Operation and Maintenance Data
  • Functional Goals: Operation and Maintenance Documentation, Indoor Air Quality, and Safety and Security Documentation
  • Construction Documentation BIM application Goal:
    • Design Concept Phase — AE
    • Design Development (DD) Phase — AE
    • Construction Documents (CD) Phase — AE
    • Construction Delivery Phase — GC
    • Closeout Phase (As-Built and Record Drawings) — GC/AE


  • Timeline Goal: To Be Completed at Each of the Institution's 20 Commercial Sites By June 2022
  • Maintenance Goal: to Be in Sync with the Institution’s Computerized Maintenance Management Software (CMMS) System

DESIGN CRITERIA

  • The IPD Team Shall Be Facilitated By a Third-Party BIM Software Contractor
  • The IPD Team Shall Include Each Building’s Office Manager, Building Facility Manager, and Third-Party BIM Service Consultant to Facilitate this Project
  • The IPD Approach will Include Architects, Structural Consultants, and Mechanical Engineer Consultants
  • The IPD Team Shall Include Corporate Management’s Building Committee of Building Managers, Leasing Manager, and Capital Projects Manager
  • The IPD Team Shall Include the Facility Manager and New Corporate BIM Manager
  • The IPD Team Shall Design-Construct, Operate, and Maintain BIM Contract Document Standards for All Future Capital Projects, New and Tenant Fit-Out
  • The IPD Team’s BIM Standards Shall not Include the Leasing Agreement Layer Documenting the Square Footages, Leasing Start and End Date, and the Cost per Square Foot
  • The IPD Team will Establish BIM Security and Resiliency Layer and will Include the Site Plan Showing Potential Security Concerns, e.g., Air Intakes
  • Two-Dimensional Building Elevations Shall Be Included in Record Drawings
  • The BIM Service Consultant Shall Coordinate a Barcoding Process in Sync with the Corporate Facility Manager’s CMMS

- ANSWERS marked in blue -

Project Delivery Method:

  • Design-Build (D-B)
  • Integrated Project Delivery (IPD)
  • Construction
  • Design-Bid-Build (D-B-B)
  • Performance Contract (PC)

Owner Team:

  • Company CEO
  • Building Committee
  • Owner Representative
  • In-House Architect

Project Delivery Team:

  • Construction Manager
  • BIM Services Consultant
  • BIM CAD Operator
  • O&M Staff
  • Individual On-Site Project Team Members
  • Government Agency

Application 2019 ASHRAE Handbook

  • Fundamentals 2017 Handbook
  • Refrigeration 2018 Handbook
  • HVAC Applications 2019 ASHRAE Handbook
  • HVAC System and Equipment 2020 ASHRAE Handbook

Other References:

  • Codes and Standards in the Back of Each ASHRAE Handbook for Additional Information
  • U.S. General Services Administration (GSA) Guidelines for BIM Software
  • Construction Management Association of America (CMAA)
  • International Organization for Standardization (ISO) Building Information Modeling Standards

DESIGN INTENT DOCUMENT

  • A Commercial Building Institution Makes a Corporate Decision to Update all its Building Record Drawings to 3D BIM Computer-Aided Drawings (CAD)
  • This Institution Makes a Corporate Decision to Mandate All Future Building Programs Shall Be Completed using 3D BIM CAD Software to Generate Contract Drawings
  • The Project Delivery will Be Design-Bid-Build for All Future Projects
  • BIM Standards Shall Include the Institution’s Standard Layers Documenting Operation and Maintenance Data
  • Functional Goals: Operation and Maintenance Documentation, Indoor Air Quality, and Safety and Security Documentation
  • Construction Documentation BIM application Goal:
    • Design Concept Phase — AE
    • Design Development (DD) Phase — AE
    • Construction Documents (CD) Phase — AE
    • Construction Delivery Phase — GC
    • Closeout Phase (As-Built and Record Drawings) — GC / AE


  • Timeline Goal: To Be Completed at Each of the Institution's 20 Commercial Sites By June 2022
  • Maintenance Goal: to Be in Sync with the Institution’s Computerized Maintenance Management Software (CMMS) System

DESIGN CRITERIA

  • The IPD Team Shall Be Facilitated By a Third-Party BIM Software Contractor
  • The IPD Team Shall Include Each Building’s Office Manager, Building Facility Manager, and Third-Party BIM Service Consultant to Facilitate this Project
  • The IPD Approach will Include Architects, Structural Consultants, and Mechanical Engineer Consultants
  • The IPD Team Shall Include Corporate Management’s Building Committee of Building Managers, Leasing Manager, and Capital Projects Manager
  • The IPD Team Shall Include the Facility Manager and New Corporate BIM Manager
  • The IPD Team Shall Design-Construct, Operate, and Maintain BIM Contract Document Standards for All Future Capital Projects, New and Tenant Fit-Out
  • The IPD Team’s BIM Standards Shall not Include the Leasing Agreement Layer Documenting the Square Footages, Leasing Start and End Date, and the Cost per Square Foot
  • The IPD Team will Establish BIM Security and Resiliency Layer and will Include the Site Plan Showing Potential Security Concerns, e.g., Air Intakes
  • Two-Dimensional Building Elevations Shall Be Included in Record Drawings
  • The BIM Service Consultant Shall Coordinate a Barcoding Process in Sync with the Corporate Facility Manager’s CMMS