Phase One
Design and construction for phase one consisted of office and support spaces; core mechanical, electrical, and utility spaces; and the “mother grow room” and propagation chamber for the genetic stock of all the plants. These prefabricated rooms were delivered to the site and then connected to all utilities, including reverse osmosis (RO) water. The mother chamber was operational by February, allowing MedPharm to begin growing breeding stock while the next two phases were being designed and built.
All infrastructure that would be needed for phases two and three was also installed during phase one. This included all AHUs, chillers, electrical gear, emergency generator, water service, sanitary sewer, and natural gas. The portion of the fire protection system serving phase one also was operational, allowing the city to issue a certificate of occupancy to MedPharm so that it could begin operations.
Phase Two
The facility’s vegetation and flower rooms and related support spaces were designed and constructed in phase two and came online in June — in time to receive the first crop of plants from the mother grow chamber.
This phase, which connected each room to the building infrastructure installed during phase one, required several design iterations for grow lighting specifications, lighting layout, as well as HVAC systems, primarily the cooling and dehumidification systems. Lighting, temperature, and humidity are critical for these rooms, as any deviation from acceptable levels puts the entire crop at risk for lower yields and/or disease, costing the owner in wasted resources, time, and revenue. Thus, sensors constantly monitor room conditions, and all mechanical and electrical systems have redundancy. A CO2 enrichment system was also designed and utilized for the grow rooms.
Phase Three
The final stage of the project provided design and construction of the extraction, quality control, and packaging spaces. These areas are essentially a lab space in which employees separate the oils from the dry cannabis matter and package the final products, which come in the form of creams, pills, and drops.
This stage required attention to all utility and safety requirements for the processing and lab equipment along with close coordination with the owner and equipment manufacturers.
With the spaces and lab and process equipment fully defined, the design team reconciled the actual phase-three HVAC loads with the system assumptions made early in the project. IMEG collaborated with the contractor to ensure the final HVAC design remained within the project budget and schedule.