Back 2 Basics
Project Delivery Method: Integrated project delivery (IPD)
Project Type: Tenant fit-out
Owner Team: Building owner, owner representative (consultant), facility manager (outsource staff), and building automation system (BAS) on-site technician
Project Delivery Team: IPD project manager, job superintendent, and mechanical-electrical coordinator as well as an HVAC lead designer and architect, plumbing, and electrical consultants
HVAC Project Team: HVAC contractor project manager; subcontractor; automatic temperature control (ATC) technician; operation and maintenance (O&M) technician (outsource staff); third-party commissioning consultant (CxC); and testing, adjusting, and balancing (TAB) technician
Application 2019 ASHRAE Handbook: Commercial and Public Buildings, Chapter 3
Systems and Equipment 2020 ASHRAE Handbook: Radiant Heating and Cooling, Chapter 6
References: 2019 ASHRAE Handbook – Applications and 2020 ASHRAE Handbook – HVAC Systems and Equipment, Chapter 13, Hydronic Heating and Cooling
Other References: The codes and standards located in the back of each ASHRAE Handbook, ASHRAE standard practice for inspection and maintenance of commercial building HVAC systems, ASHRAE Standard 55 (Thermal Environmental Conditions for Human Occupancy), ASHRAE Standard 62.1 (IAQ), and ASHRAE Standard 202 (Commissioning Process for Buildings and Systems)
The HVAC system selection and design intent is based on the process outlined in ASHRAE Handbook 2020, Chapter 1, HVAC System Analysis and Selection, and includes the following:
Program and Project Goals:
Existing Conditions: