Project Type: Existing conditions and heating system failure
References: Internet browser search engine for temporary heating equipment, U.S. Occupational Safety and Health Administration (OSHA) 1926.54 on temporary heating devices, and OSHA safety manual, temporary heat
DESIGN INTENT DOCUMENT (DID)
An unexpected heating system failure on the south side of a K-8, one-story series of classrooms resulting in no hot water heating to the perimeter. The school department, along with its facility staff, implemented an IPD project delivery method with a local heating company service department to provide temporary heat and ventilation to six classrooms for one week while the heating system was repaired.
The IPD team followed the ASHRAE Handbook 2020, Chapter 1, “HVAC System Analysis and Selection” process as it pertains to space and occupational comfort and (IAQ), including the following:
Owner environmental health and safety (EH&S) program goals and additional goals
Process/system constraints
School safety and security program requirements
OSHA guidelines specifically drafted for temporary heating devices and safety
Emergency operating budget and project timeline schedule
Existing Conditions:
The central air system supply and return air cfm to remain in operation serving the entire first floor of the building
Individual perimeter classroom unit ventilators with hot water heating coils with room thermostats
A failed perimeter hot water heating zone pump serving six classroom unit ventilators
Available utilities include electricity for permanent and emergency temporary power
Provide temporary heat and additional ventilation to the classrooms for one week while a hot water heating system zone pump is purchased, delivered, and installed in place of the existing in-line circulator.
DESIGN CRITERIA DOCUMENT
The HVAC design criteria shall be in sync with the project delivery method and the owner’s project requirements.
The design criteria shall be based on maintaining space comfort and ventilation air using individual temporary electric heaters, two per room, powered by 208-3-60 temporary electricity.
In addition to existing ventilation to classrooms, the school will use operable sash windows to supplement outdoor air previously provided through each unit ventilator’s minimum ventilation damper and louver.
Rented electric floor mounted heaters shall be 2-20 kW, fan-powered, and with MERV-14 filters.
Each classroom shall have a temporary space thermostat to serve the two electric temporary heaters, and the thermostat shall be set at 68°F
The heating IPD contractor shall produce a conceptual scope of work as follows:
The contractor’s design engineer shall provide system flow diagrams showing the system repair work along with temporary heating drawings that show the electrical power wiring per code and the location of the two electric heaters per classroom.
This design engineer shall include electrical heater equipment data sheets as well as the new replacement hot water heating circulator.
ASHRAE Standard 55 (Thermal Environmental Conditions for Human Occupancy)
ASHRAE Standard 62.1 (IAQ)
ASHRAE Standard 90.1 (Minimum Energy Standards)
OSHA 1926.54 on Temporary Heating devices
OSHA Safety Manual, Temporary Heat Safety
DESIGN INTENT DOCUMENT
An unexpected heating system failure on the south side of a K-8, one-story series of classrooms resulting in no HVAC to the perimeter
The IPD team followed the ASHRAE Handbook 2020, Chapter 1, “HVAC System Analysis and Selection” process as it pertains to space and occupational comfort as well as IAQ
Owner environmental health and safety (EH&S) program goals and additional goals
D-B process/system constraints
School safety and security program requirements
OSHA guidelines specifically drafted for temporary heating devices and safety
Annual school operating budget and project timeline schedule
Existing Conditions:
Central air system supply and return air cfm to remain in operation serving the entire first floor of the building
Individual perimeter classroom unit ventilators with hot water heating coils and room thermostats
Failed perimeter 2-pipe heating and cooling water zone pump serving six classroom unit ventilators
Utility Availabilities:
Hot water heating system temporary distribution
Electricity for permanent and emergency temporary power
Provide temporary heat and additional ventilation to the classrooms for one week while a hot water heating system zone pump is purchased, delivered, and installed in place of the existing in-line circulator.
DESIGN CRITERIA DOCUMENT
The HVAC design criteria shall be in sync with the project delivery method and owner’s building program requirements
The design criteria shall be based on ASHRAE 60.2 and federal energy code compliance for outdoor air temperature compliance
The existing HVAC systems serving the renovated offices and conference rooms shall be removed in their entirety, and a new VRF heating and air conditioning system shall be installed
Utilities shall be 480/3/60 electrical power to serve two DOAS units, 75-ton units each sized with the new automatic controls shall be interfaced with the existing BAS system
The air filters shall be pre-filter MERV-7 and final filter MERV-15, serving the new DOAS unit and MERV-14 fan coil unit (FCU) filters.
The new automatic controls shall be interfaced with the existing BAS system.
The low-velocity sheet metal distribution shall be reused
Each office and conference room shall have its own programmable thermostat set at 68°F heating and 76° cooling in the occupied cycle and 60° heating and 76° unoccupied set points.
- ANSWERS marked in blue -
Project Delivery Method:
Design-Build (D-B)
Integrated Project Delivery (IPD)
Design-Bid-Build (D-B-B)
Owner Team:
Local School Department
Building Program Committee
Internal Owner Representative
Owner Representative (consultant)
Project Manager of Capital Projects
Facility Manager (in-house staff)
Project Delivery Team:
IPD Project Manager
Mechanical-Electrical Coordinator
Equipment Manufacturer Technician
Utility Company Representative
Architect, Acoustical, Plumbing, Electrical, Structural, Fire Protection, and Security Consultants
HVAC Supervisor (in-house staff)
HVAC Supervisor (contractor)
ATC Technician (contractor)
Building automation system (BAS) Technician (in-house staff)
Operations and maintenance (O&M) Technician (in-house staff)
Third-Party Commissioning Consultant (CxC)
Testing, Adjusting, and Balancing (TAB) Technician
ASHRAE Standard 55 (Thermal Environmental Conditions for Human Occupancy)
ASHRAE Standard 62.1 (IAQ)
ASHRAE Standard 90.1 (Minimum Energy Standards)
OSHA 1926.54 on Temporary Heating devices
OSHA Safety Manual, Temporary Heat Safety
DESIGN INTENT DOCUMENT
An unexpected heating system failure on the south side of a K-8, one-story series of classrooms resulting in no HVAC to the perimeter
The IPD team followed the ASHRAE Handbook 2020, Chapter 1, “HVAC System Analysis and Selection” process as it pertains to space and occupational comfort as well as IAQ
Owner environmental health and safety (EH&S) program goals and additional goals
D-B process/system constraints
School safety and security program requirements
OSHA guidelines specifically drafted for temporary heating devices and safety
Annual school operating budget and project timeline schedule
Existing Conditions:
Central air system supply and return air cfm to remain in operation serving the entire first floor of the building
Individual perimeter classroom unit ventilators with hot water heating coils and room thermostats
Failed perimeter 2-pipe heating and cooling water zone pump serving six classroom unit ventilators
Utility Availabilities:
Hot water heating system temporary distribution
Electricity for permanent and emergency temporary power
Provide temporary heat and additional ventilation to the classrooms for one week while a hot water heating system zone pump is purchased, delivered, and installed in place of the existing in-line circulator.
DESIGN CRITERIA DOCUMENT
The HVAC design criteria shall be in sync with the project delivery method and owner’s building program requirements
The design criteria shall be based on ASHRAE 60.2 and federal energy code compliance for outdoor air temperature compliance
The existing HVAC systems serving the renovated offices and conference rooms shall be removed in their entirety, and a new VRF heating and air conditioning system shall be installed
Utilities shall be 480/3/60 electrical power to serve two DOAS units, 75-ton units each sized with the new automatic controls shall be interfaced with the existing BAS system
The air filters shall be pre-filter MERV-7 and final filter MERV-15, serving the new DOAS unit and MERV-14 fan coil unit (FCU) filters.
The new automatic controls shall be interfaced with the existing BAS system.
The low-velocity sheet metal distribution shall be reused
Each office and conference room shall have its own programmable thermostat set at 68°F heating and 76° cooling in the occupied cycle and 60° heating and 76° unoccupied set points.