College Study Hall Renovation VAV System Using Construction Management Project Delivery

SCROLL

CoolProject Delivery Method: Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)

Owner Team: College president, owner representative (consultant), project manager of capital project, and facility manager (in-house staff)

Project Delivery Team: CM project manager; job superintendent; mechanical-electrical coordinator; and architect, acoustical, plumbing, electrical, structural, fire protection, and security consultants

HVAC Project Team: HVAC project manager-subcontractor; building automation system (BAS) technician (in-house staff); BAS technician-subcontractor; operations and maintenance (O&M) technician (in-house staff); third-party commissioning consultant (CxC); and testing, adjusting, and balancing (TAB) technician


Application 2019 ASHRAE Handbook: Places of Assembly, Chapter 5; Educational Facilities, Chapter 8; and Museums, Galleries, Archives, and Libraries, Chapter 24

Systems 2020 ASHRAE Handbook: HVAC System Analysis and Selection, Chapter 1; Decentralized Cooling and Heating, Chapter 2; and Air-Handling and Distribution, Chapter 4

Equipment 2020 ASHRAE Handbook: Room Air Distribution Equipment, Chapter 20

Project Type: Renovation

References: 2017 ASHRAE Handbook, Fundamentals; 2019 ASHRAE Handbook, HVAC Applications; 2020 ASHRAE Handbook, HVAC Systems and Equipment; and refer to the codes and standards in the back of each ASHRAE Handbook for additional reference

Other References: ASHRAE GreenGuide: Design, Construction, and Operation of Sustainable; ASHRAE Humidity Control Design Guide for Commercial and Institutional Buildings; ASHRAE Standard 55 (Thermal Environmental Conditions for Human Occupancy); ASHRAE Standard 62.1 (IAQ); ASHRAE Standard 202 (Commissioning Process for Buildings and Systems); and Construction Management Association of America (CMAA)

DESIGN INTENT DOCUMENT (DID)

  • The HVAC system selection and design intent is based on the processes outlined in ASHRAE Handbook 2020, Chapter 1, HVAC System Analysis and Selection, and includes the following:

    • College building program goals and additional goals

    • System and constructability constraints

    • The finalized system selection shall be decentralized HVAC, decentralized HVAC air systems, and terminal units — both variable air volume (VAV) and fan-powered box (FPB)

    • New automatic temperature controls (ATC), VAV, and FPB furnished controls; a BACnet interface; an internet interface; an existing BAS interface; and an existing computerized maintenance management software (CMMS) system interface

  • Program & Project Goals:

    • Functional goals: refer to Chapter 1, 2020 Handbook

    • Budget goals: first cost and operating cost

    • Timeline goal(s): occupancy due date — August, before classes start

    • Management goals: In-house; capital projects; and mechanical, electrical operation, and maintenance management

  • Utility availabilities: existing electrical power, central plant chilled water and hot water heating, and BAS

  • Existing conditions: Remove and replace the central air system supply air, return air, and economizer air cubic feet per minute (cfm) as well as the general exhaust

  • Heating system(s): Two-pipe, hot water supply (HWS) and hot water return (HWR) to certain VAV terminals with heating coils and FPBs with heating coils

  • Air conditioning system(s): A new 24,000-cfm central air system with a barometric relief economizer, chilled water coil, and variable-speed drive (VSD) supply fan

  • Outdoor air ventilation system(s): minimum, air-side economizer, and 100% outside air and steam humidifier

  • Central air systems: Single duct with multiple zones and terminal units with combination of constant volume and VAV with a minimum supply air set point

  • Air filters: MERV-7 pre-filter, MERV-14 final filter, and MERV-14 FPB unit filters

  • Terminal units: VAV and FPB with wall registers, ceiling diffusers, and return air plenum

DESIGN CRITERIA DOCUMENT

  • The HVAC design criteria shall be in sync with the project delivery method and owner’s project requirements

  • The design criteria shall be based on ASHRAE 90.1 and state energy code compliance for outdoor air temperature compliance

  • A new central air system will replace the existing unit to provide improved HVAC to the renovation space being converted to a study hall on the college campus building

  • The space shall be maintained at 68°F in the occupied periods and 60° during the unoccupied heating season. In the cooling season, the space shall be 75° in the occupied period and 78° in the unoccupied period

  • Space humidity will be provided by a steam humidifier located in the new central air discharge duct with 20-foot aluminum sheet metal to maintain 30% RH in the heating season

  • Depending on the occupied spaces, e.g., study cubicles, private study rooms, and conference rooms, the air terminals will be either VAV, constant volume (CV) with perimeter heating, FPB with minimum air set point, or CV with heating coil

  • The design team shall provide contract drawings and specification coordinated with equipment weight, electric, and plumbing criteria to solicit contractor bids

  • Field fabrication drawings shall become the record drawings at closeout

  • VAV and FPB terminals shall be furnished with O&M manuals

  • The preventive maintenance work orders shall be uploaded to the in-house O&M CMMS.

  • The design team and CM firm will refer to ASHRAE guidelines for ventilation and humidity control and ASHRAE Indoor-Air Quality Guide: Best Practice for Design, Construction, and Commissioning

Image courtesy of Unsplash

Design Engineer’s Punchlist

Project Delivery Method:

  • Design-Build (D-B)

  • Integrated Project Delivery (IPD)

  • Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)

  • Design-Bid-Build (D-B-B)

Owner Team:

  • College President

  • Building Program Committee

  • Owner Representative (consultant)

  • Project Manager of Capital Projects

Project Delivery Team:

  • Design-Build (D-B) Project Manager

  • Construction Management (CM) Project Manager

  • Design-Bid-Build (D-B-B) Project Manager

  • Job Superintendent

  • Mechanical-Electrical Coordinator

  • Architect, Acoustical, Plumbing, Electrical, Structural, Fire Protection, and Security Consultants

HVAC Project Team:

  • HVAC Project Manager-Subcontractor

  • HVAC Technician (in-house staff)

  • BAS Technician (in-house staff)

  • Third-Party Commissioning Consultant (CxC)

  • Third-Party TAB (Testing, Adjusting, and Balancing) Technician

Application 2019 ASHRAE Handbook

  • Commercial and Public Buildings, Chapter 3

  • Places of Assembly, Chapter 5

  • Educational Facilities, Chapter 8

  • Museums, Galleries, Archives, and Libraries, Chapter 24

  • Ventilation of Industrial Environment, Chapter 32

Systems 2020 ASHRAE Handbook

  • HVAC System Analysis and Selection, Chapter 1

  • Decentralized Cooling and Heating, Chapter 2

  • Central Cooling and Heating Plant, Chapter 3

  • Air-Handling and Distribution, Chapter 4

  • In-Room Terminal Systems, Chapter 5

Equipment 2020 ASHRAE Handbook

  • Room Air Distribution Equipment, Chapter 20

  • Fans, Chapter 21

  • Air Heating Coils, Chapter 27

  • Heat Exchangers, Chapter 48

Project Type:

  • New Construction

  • Addition

  • Renovation

  • Shell & Core

  • Infrastructure (central heating and cooling)

References:

  • 2017 ASHRAE Handbook – Fundamentals

  • 2018 ASHRAE Handbook – Refrigeration

  • 2019 ASHRAE Handbook – HVAC Applications

  • 2020 ASHRAE Handbook – HVAC Systems and Equipment

Other References:

  • ASHRAE Guide for Buildings in Hot & Humid Climates

  • ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning

  • ASHRAE Practical Guide to Seismic Restraints

  • ASHRAE Standard 202 (Commissioning Process for Buildings and Systems)

DESIGN INTENT DOCUMENT (DID)

  • College Building Program Goals and Additional Goals

  • New Automatic Temperature Controls (ATC), VAV, and FPB Furnished Controls; and BACnet, Internet, Existing BAS, and Existing CMMS System Interfaces

  • Functional Goals: Refer to Chapter 1, 2019 Handbook

  • Budget Goals: First Cost and Operating Cost

  • Timeline Goal(s): Occupancy Due Date: August Before Classes Start

  • Management Goals: Outsource Management and Capital Projects Management

  • Utility Availabilities: Existing Electrical Emergency Power, Central Plant Condenser Water, and BAS

  • Existing Conditions: Remove and Replace Central Air System Supply Air, Return Air, and Economizer Air Cubic Feet Per Minute (cfm) and General Exhaust

  • Heating System(s): 2-Pipe, Hot Water Supply (HWS) and Hot Water Return (HWR) to Certain VAV Terminals with Heating Coils and FPBs with Heating Coils

  • Terminal Units: VAV and FPB with Wall Registers, Ceiling Diffusers, and Return Air Plenum

DESIGN CRITERIA DOCUMENT

  • The HVAC Design Criteria Shall Be in Sync with the Project Delivery Method and Owner’s Project Requirements

  • A New Central Air System will Replace the Existing Unit to Provide Improved HVAC to the Renovation Space Being Converted to a Study Hall on the College Campus Building

  • The Space Shall Be Maintained at 68°F in the Occupied Periods and 60° During the Unoccupied Heating Season. In the Cooling Season, the Space Shall Be 78° in the Occupied Period and 75° in the Unoccupied Period

  • The HVAC Team Shall Provide Contract Drawings and Specification Coordinated with Equipment Weight, Electric, and Plumbing Criteria to Solicit Contractor Bids

  • Field Fabrication Drawings Shall Become the Record Drawings at Closeout

  • VAV and FPB Terminals Shall Be Furnished with O&M Manuals

  • The Preventive Maintenance Work Orders Shall Be Uploaded to the In-House O&M CMMS System

  • The Design Team and CM Firm Will Refer to ASHRAE guidelines for Ventilation and Humidity Control and ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning

- ANSWERS marked in blue -

Project Delivery Method:

  • Design-Build (D-B)

  • Integrated Project Delivery (IPD)

  • Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)

  • Design-Bid-Build (D-B-B)

Owner Team:

  • College President

  • Building Program Committee

  • Owner Representative (consultant)

  • Project Manager of Capital Projects

Project Delivery Team:

  • Design-Build (D-B) Project Manager

  • Construction Management (CM) Project Manager

  • Design-Bid-Build (D-B-B) Project Manager

  • Job Superintendent

  • Mechanical-Electrical Coordinator

  • Architect, Acoustical, Plumbing, Electrical, Structural, Fire Protection, and Security Consultants

HVAC Project Team:

  • HVAC Project Manager-Subcontractor

  • HVAC Technician (in-house staff)

  • BAS Technician (in-house staff)

  • Third-Party Commissioning Consultant (CxC)

  • Third-Party TAB (Testing, Adjusting, and Balancing) Technician

Application 2019 ASHRAE Handbook

  • Commercial and Public Buildings, Chapter 3

  • Places of Assembly, Chapter 5

  • Educational Facilities, Chapter 8

  • Museums, Galleries, Archives, and Libraries, Chapter 24

  • Ventilation of Industrial Environment, Chapter 32

Systems 2020 ASHRAE Handbook

  • HVAC System Analysis and Selection, Chapter 1

  • Decentralized Cooling and Heating, Chapter 2

  • Central Cooling and Heating Plant, Chapter 3

  • Air-Handling and Distribution, Chapter 4

  • In-Room Terminal Systems, Chapter 5

Equipment 2020 ASHRAE Handbook

  • Room Air Distribution Equipment, Chapter 20

  • Fans, Chapter 21

  • Air Heating Coils, Chapter 27

  • Heat Exchangers, Chapter 48

Project Type:

  • New Construction

  • Addition

  • Renovation

  • Shell & Core

  • Infrastructure (central heating and cooling)

References:

  • 2017 ASHRAE Handbook – Fundamentals

  • 2018 ASHRAE Handbook – Refrigeration

  • 2019 ASHRAE Handbook – HVAC Applications

  • 2020 ASHRAE Handbook – HVAC Systems and Equipment

Other References:

  • ASHRAE Guide for Buildings in Hot & Humid Climates

  • ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning

  • ASHRAE Practical Guide to Seismic Restraints

  • ASHRAE Standard 202 (Commissioning Process for Buildings and Systems)

DESIGN INTENT DOCUMENT (DID)

  • College Building Program Goals and Additional Goals

  • New Automatic Temperature Controls (ATC), VAV, and FPB Furnished Controls; and BACnet, Internet, Existing BAS, and Existing CMMS System Interfaces

  • Functional Goals: Refer to Chapter 1, 2019 Handbook

  • Budget Goals: First Cost and Operating Cost

  • Timeline Goal(s): Occupancy Due Date — August Before Classes Start

  • Management Goals: Outsource Management and Capital Projects Management

  • Utility Availabilities: Existing Electrical Emergency Power, Central Plant Condenser Water, and BAS

  • Existing Conditions: Remove and Replace Central Air System Supply Air, Return Air, and Economizer Air Cubic Feet Per Minute (cfm) and General Exhaust

  • Heating System(s): 2-Pipe, Hot Water Supply (HWS) and Hot Water Return (HWR) to Certain VAV Terminals with Heating Coils and FPBs with Heating Coils

  • Terminal Units: VAV and FPB with Wall Registers, Ceiling Diffusers, and Return Air Plenum

DESIGN CRITERIA DOCUMENT

  • The HVAC Design Criteria Shall Be in Sync with the Project Delivery Method and Owner’s Project Requirements

  • A New Central Air System will Replace the Existing Unit to Provide Improved HVAC to the Renovation Space Being Converted to a Study Hall on the College Campus Building

  • The Space Shall Be Maintained at 68° in the Occupied Periods and 60° During Unoccupied Heating Season. In the Cooling Season, the Space Shall Be 78° in the Occupied Period and 75° in the Unoccupied Period

  • The HVAC Team Shall Provide Contract Drawings and Specification Coordinated with Equipment Weight, Electric, and Plumbing Criteria to Solicit Contractor Bids

  • Field Fabrication Drawings Shall Become the Record Drawings at Closeout

  • VAV and FPB Terminals Shall Be Furnished with O&M Manuals

  • The Preventive Maintenance Work Orders Shall Be Uploaded to the In-House O&M CMMS System

  • The Design Team and CM Firm Will Refer to ASHRAE guidelines for Ventilation and Humidity Control and ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning