Back2Basics
CoolProject Delivery Method: Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)
Owner Team: College president, owner representative (consultant), project manager of capital project, and facility manager (in-house staff)
Project Delivery Team: CM project manager; job superintendent; mechanical-electrical coordinator; and architect, acoustical, plumbing, electrical, structural, fire protection, and security consultants
HVAC Project Team: HVAC project manager-subcontractor; building automation system (BAS) technician (in-house staff); BAS technician-subcontractor; operations and maintenance (O&M) technician (in-house staff); third-party commissioning consultant (CxC); and testing, adjusting, and balancing (TAB) technician
Application 2019 ASHRAE Handbook: Places of Assembly, Chapter 5; Educational Facilities, Chapter 8; and Museums, Galleries, Archives, and Libraries, Chapter 24
Systems 2020 ASHRAE Handbook: HVAC System Analysis and Selection, Chapter 1; Decentralized Cooling and Heating, Chapter 2; and Air-Handling and Distribution, Chapter 4
Equipment 2020 ASHRAE Handbook: Room Air Distribution Equipment, Chapter 20
Project Type: Renovation
References: 2017 ASHRAE Handbook, Fundamentals; 2019 ASHRAE Handbook, HVAC Applications; 2020 ASHRAE Handbook, HVAC Systems and Equipment; and refer to the codes and standards in the back of each ASHRAE Handbook for additional reference
Other References: ASHRAE GreenGuide: Design, Construction, and Operation of Sustainable; ASHRAE Humidity Control Design Guide for Commercial and Institutional Buildings; ASHRAE Standard 55 (Thermal Environmental Conditions for Human Occupancy); ASHRAE Standard 62.1 (IAQ); ASHRAE Standard 202 (Commissioning Process for Buildings and Systems); and Construction Management Association of America (CMAA)
The HVAC system selection and design intent is based on the processes outlined in ASHRAE Handbook 2020, Chapter 1, HVAC System Analysis and Selection, and includes the following:
College building program goals and additional goals
System and constructability constraints
The finalized system selection shall be decentralized HVAC, decentralized HVAC air systems, and terminal units — both variable air volume (VAV) and fan-powered box (FPB)
New automatic temperature controls (ATC), VAV, and FPB furnished controls; a BACnet interface; an internet interface; an existing BAS interface; and an existing computerized maintenance management software (CMMS) system interface
Program & Project Goals:
Functional goals: refer to Chapter 1, 2020 Handbook
Budget goals: first cost and operating cost
Timeline goal(s): occupancy due date — August, before classes start
Management goals: In-house; capital projects; and mechanical, electrical operation, and maintenance management
Utility availabilities: existing electrical power, central plant chilled water and hot water heating, and BAS
Existing conditions: Remove and replace the central air system supply air, return air, and economizer air cubic feet per minute (cfm) as well as the general exhaust
Heating system(s): Two-pipe, hot water supply (HWS) and hot water return (HWR) to certain VAV terminals with heating coils and FPBs with heating coils
Air conditioning system(s): A new 24,000-cfm central air system with a barometric relief economizer, chilled water coil, and variable-speed drive (VSD) supply fan
Outdoor air ventilation system(s): minimum, air-side economizer, and 100% outside air and steam humidifier
Central air systems: Single duct with multiple zones and terminal units with combination of constant volume and VAV with a minimum supply air set point
Air filters: MERV-7 pre-filter, MERV-14 final filter, and MERV-14 FPB unit filters
Terminal units: VAV and FPB with wall registers, ceiling diffusers, and return air plenum
The HVAC design criteria shall be in sync with the project delivery method and owner’s project requirements
The design criteria shall be based on ASHRAE 90.1 and state energy code compliance for outdoor air temperature compliance
A new central air system will replace the existing unit to provide improved HVAC to the renovation space being converted to a study hall on the college campus building
The space shall be maintained at 68°F in the occupied periods and 60° during the unoccupied heating season. In the cooling season, the space shall be 75° in the occupied period and 78° in the unoccupied period
Space humidity will be provided by a steam humidifier located in the new central air discharge duct with 20-foot aluminum sheet metal to maintain 30% RH in the heating season
Depending on the occupied spaces, e.g., study cubicles, private study rooms, and conference rooms, the air terminals will be either VAV, constant volume (CV) with perimeter heating, FPB with minimum air set point, or CV with heating coil
The design team shall provide contract drawings and specification coordinated with equipment weight, electric, and plumbing criteria to solicit contractor bids
Field fabrication drawings shall become the record drawings at closeout
VAV and FPB terminals shall be furnished with O&M manuals
The preventive maintenance work orders shall be uploaded to the in-house O&M CMMS.
The design team and CM firm will refer to ASHRAE guidelines for ventilation and humidity control and ASHRAE Indoor-Air Quality Guide: Best Practice for Design, Construction, and Commissioning
Image courtesy of Unsplash
Design-Build (D-B)
Integrated Project Delivery (IPD)
Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)
Design-Bid-Build (D-B-B)
College President
Building Program Committee
Owner Representative (consultant)
Project Manager of Capital Projects
Design-Build (D-B) Project Manager
Construction Management (CM) Project Manager
Design-Bid-Build (D-B-B) Project Manager
Job Superintendent
Mechanical-Electrical Coordinator
Architect, Acoustical, Plumbing, Electrical, Structural, Fire Protection, and Security Consultants
HVAC Project Manager-Subcontractor
HVAC Technician (in-house staff)
BAS Technician (in-house staff)
Third-Party Commissioning Consultant (CxC)
Third-Party TAB (Testing, Adjusting, and Balancing) Technician
Commercial and Public Buildings, Chapter 3
Places of Assembly, Chapter 5
Educational Facilities, Chapter 8
Museums, Galleries, Archives, and Libraries, Chapter 24
Ventilation of Industrial Environment, Chapter 32
HVAC System Analysis and Selection, Chapter 1
Decentralized Cooling and Heating, Chapter 2
Central Cooling and Heating Plant, Chapter 3
Air-Handling and Distribution, Chapter 4
In-Room Terminal Systems, Chapter 5
Room Air Distribution Equipment, Chapter 20
Fans, Chapter 21
Air Heating Coils, Chapter 27
Heat Exchangers, Chapter 48
New Construction
Addition
Renovation
Shell & Core
Infrastructure (central heating and cooling)
2017 ASHRAE Handbook – Fundamentals
2018 ASHRAE Handbook – Refrigeration
2019 ASHRAE Handbook – HVAC Applications
2020 ASHRAE Handbook – HVAC Systems and Equipment
ASHRAE Guide for Buildings in Hot & Humid Climates
ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning
ASHRAE Practical Guide to Seismic Restraints
ASHRAE Standard 202 (Commissioning Process for Buildings and Systems)
College Building Program Goals and Additional Goals
New Automatic Temperature Controls (ATC), VAV, and FPB Furnished Controls; and BACnet, Internet, Existing BAS, and Existing CMMS System Interfaces
Functional Goals: Refer to Chapter 1, 2019 Handbook
Budget Goals: First Cost and Operating Cost
Timeline Goal(s): Occupancy Due Date: August Before Classes Start
Management Goals: Outsource Management and Capital Projects Management
Utility Availabilities: Existing Electrical Emergency Power, Central Plant Condenser Water, and BAS
Existing Conditions: Remove and Replace Central Air System Supply Air, Return Air, and Economizer Air Cubic Feet Per Minute (cfm) and General Exhaust
Heating System(s): 2-Pipe, Hot Water Supply (HWS) and Hot Water Return (HWR) to Certain VAV Terminals with Heating Coils and FPBs with Heating Coils
Terminal Units: VAV and FPB with Wall Registers, Ceiling Diffusers, and Return Air Plenum
The HVAC Design Criteria Shall Be in Sync with the Project Delivery Method and Owner’s Project Requirements
A New Central Air System will Replace the Existing Unit to Provide Improved HVAC to the Renovation Space Being Converted to a Study Hall on the College Campus Building
The Space Shall Be Maintained at 68°F in the Occupied Periods and 60° During the Unoccupied Heating Season. In the Cooling Season, the Space Shall Be 78° in the Occupied Period and 75° in the Unoccupied Period
The HVAC Team Shall Provide Contract Drawings and Specification Coordinated with Equipment Weight, Electric, and Plumbing Criteria to Solicit Contractor Bids
Field Fabrication Drawings Shall Become the Record Drawings at Closeout
VAV and FPB Terminals Shall Be Furnished with O&M Manuals
The Preventive Maintenance Work Orders Shall Be Uploaded to the In-House O&M CMMS System
The Design Team and CM Firm Will Refer to ASHRAE guidelines for Ventilation and Humidity Control and ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning
Design-Build (D-B)
Integrated Project Delivery (IPD)
Construction Management @ Risk (CM) with Guaranteed Maximum Price (GMP)
Design-Bid-Build (D-B-B)
College President
Building Program Committee
Owner Representative (consultant)
Project Manager of Capital Projects
Design-Build (D-B) Project Manager
Construction Management (CM) Project Manager
Design-Bid-Build (D-B-B) Project Manager
Job Superintendent
Mechanical-Electrical Coordinator
Architect, Acoustical, Plumbing, Electrical, Structural, Fire Protection, and Security Consultants
HVAC Project Manager-Subcontractor
HVAC Technician (in-house staff)
BAS Technician (in-house staff)
Third-Party Commissioning Consultant (CxC)
Third-Party TAB (Testing, Adjusting, and Balancing) Technician
Commercial and Public Buildings, Chapter 3
Places of Assembly, Chapter 5
Educational Facilities, Chapter 8
Museums, Galleries, Archives, and Libraries, Chapter 24
Ventilation of Industrial Environment, Chapter 32
HVAC System Analysis and Selection, Chapter 1
Decentralized Cooling and Heating, Chapter 2
Central Cooling and Heating Plant, Chapter 3
Air-Handling and Distribution, Chapter 4
In-Room Terminal Systems, Chapter 5
Room Air Distribution Equipment, Chapter 20
Fans, Chapter 21
Air Heating Coils, Chapter 27
Heat Exchangers, Chapter 48
New Construction
Addition
Renovation
Shell & Core
Infrastructure (central heating and cooling)
2017 ASHRAE Handbook – Fundamentals
2018 ASHRAE Handbook – Refrigeration
2019 ASHRAE Handbook – HVAC Applications
2020 ASHRAE Handbook – HVAC Systems and Equipment
ASHRAE Guide for Buildings in Hot & Humid Climates
ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning
ASHRAE Practical Guide to Seismic Restraints
ASHRAE Standard 202 (Commissioning Process for Buildings and Systems)
College Building Program Goals and Additional Goals
New Automatic Temperature Controls (ATC), VAV, and FPB Furnished Controls; and BACnet, Internet, Existing BAS, and Existing CMMS System Interfaces
Functional Goals: Refer to Chapter 1, 2019 Handbook
Budget Goals: First Cost and Operating Cost
Timeline Goal(s): Occupancy Due Date — August Before Classes Start
Management Goals: Outsource Management and Capital Projects Management
Utility Availabilities: Existing Electrical Emergency Power, Central Plant Condenser Water, and BAS
Existing Conditions: Remove and Replace Central Air System Supply Air, Return Air, and Economizer Air Cubic Feet Per Minute (cfm) and General Exhaust
Heating System(s): 2-Pipe, Hot Water Supply (HWS) and Hot Water Return (HWR) to Certain VAV Terminals with Heating Coils and FPBs with Heating Coils
Terminal Units: VAV and FPB with Wall Registers, Ceiling Diffusers, and Return Air Plenum
The HVAC Design Criteria Shall Be in Sync with the Project Delivery Method and Owner’s Project Requirements
A New Central Air System will Replace the Existing Unit to Provide Improved HVAC to the Renovation Space Being Converted to a Study Hall on the College Campus Building
The Space Shall Be Maintained at 68° in the Occupied Periods and 60° During Unoccupied Heating Season. In the Cooling Season, the Space Shall Be 78° in the Occupied Period and 75° in the Unoccupied Period
The HVAC Team Shall Provide Contract Drawings and Specification Coordinated with Equipment Weight, Electric, and Plumbing Criteria to Solicit Contractor Bids
Field Fabrication Drawings Shall Become the Record Drawings at Closeout
VAV and FPB Terminals Shall Be Furnished with O&M Manuals
The Preventive Maintenance Work Orders Shall Be Uploaded to the In-House O&M CMMS System
The Design Team and CM Firm Will Refer to ASHRAE guidelines for Ventilation and Humidity Control and ASHRAE Indoor Air Quality Guide: Best Practice for Design, Construction, and Commissioning